This clause, known as the “ICC Force majeure Clause 2003”, is intended to apply to any contract which incorporates it either expressly or by reference. While parties are encouraged to incorporate the Clause into their contracts by its full name, it is anticipated that any reference in a contract to the ‘ICC Force majeure Clause’ shall, in the absence of evidence to the contrary, be deemed to be a reference to this Clause.

The general structure of the Clause is to provide contracting parties both with a general force majeure formula and with an off-the-peg list of force majeure events. The ICC Task Force on Force majeure and hardship discussed at length the respective merits of three options open to it. The first was simply to draft a general force majeure formula, as do the main international instruments to which the Task Force had regard, namely the united Nations Convention on Contracts for the International Sale of goods (CISg), the Principles of European Contract law, and the unidroit Principles for International Commercial Contracts. The second was to draft a general force majeure formula and to provide a merely illustrative list of force majeure events, as does the previous 1985 ICC Force majeure Clause. The third was to draft both a general force majeure formula and to provide a list of events the occurrence of which altered the evidential balance in favour of the party invoking the clause. The ICC Task Force on Force majeure and hardship has decided to draft the clause on the basis of the third option and this because of the three purposes on which the Clause is based. These three purposes are set out below.

First, it is intended that the new clause should assist the largest possible number of users: those who draft neither of such two types of such clauses in their own contracts; those who draft only a general formula but would also like the predictability of an agreed list of events; and finally those who draft only a list of specified events but who wish to invoke an unlisted event as a force majeure event.

Secondly, it is intended to give the list of events a function which goes beyond the merely illustrative, such that a party would find it easier to invoke the clause if it could point towards one of the listed events than if it could only use the general force majeure formula.

Thirdly and on the other hand, it was important not to afford a party invoking a listed event too much protection: it was definitely regarded as wrong for such a party simply to point towards the mere occurrence of a listed event, the effects of which it could reasonably have avoided or overcome, and to claim relief on that basis from its duty to perform.

The Clause seeks to attain these purposes first by providing a general force majeure formula placing the burden of proving the requirements for the application of the clause on the party invoking it. The Clause also provides a list of force majeure events, however, which is subject to the same conditions as established for the general force majeure formula but with evidential advantages for a party invoking the clause through this route. It should be emphasised that even where a party invoking the clause does so by pointing towards a listed event, that party still needs to prove that it could not reasonably have avoided or overcome the effects of the listed event.

[Page65:]

  1. Unless otherwise agreed in the contract between the parties expressly or impliedly, where a party to a contract fails to perform one or more of its contractual duties, the consequences set out in paragraphs 4 to 9 of this Clause will follow if and to the extent that that party proves:
    1. that its failure to perform was caused by an impediment beyond its reasonable control; and
    2. that it could not reasonably have been expected to have taken the occurrence of the impediment into account at the time of the conclusion of the contract; and
    3. that it could not reasonably have avoided or overcome the effects of the impediment.
  2. Where a contracting party fails to perform one or more of its contractual duties because of default by a third party whom it has engaged to perform the whole or part of the contract, the consequences set out in paragraphs 4 to 9 of this Clause will only apply to the contracting party:
    1. if and to the extent that the contracting party establishes the requirements set out in paragraph 1 of this Clause; and
    2. if and to the extent that the contracting party proves that the same requirements apply to the third party.
  3. In the absence of proof to the contrary and unless otherwise agreed in the contract between the parties expressly or impliedly, a party invoking this Clause shall be presumed to have established the conditions described in paragraph 1(a) and (b) of this Clause in case of the occurrence of one or more of the following impediments:
    1. war (whether declared or not), armed conflict or the serious threat of same (including but not limited to hostile attack, blockade, military embargo), hostilities, invasion, act of a foreign enemy, extensive military mobilisation;
    2. civil war, riot rebellion and revolution, military or usurped power, insurrection, civil commotion or disorder, mob violence, act of civil disobedience;
    3. act of terrorism, sabotage or piracy;
    4. act of authority whether lawful or unlawful, compliance with any law or governmental order, rule, regulation or direction, curfew restriction, expropriation, compulsory acquisition, seizure of works, requisition, nationalisation;
    5. act of god, plague, epidemic, natural disaster such as but not limited to violent storm, cyclone, typhoon, hurricane, tornado, blizzard, earthquake, volcanic activity, landslide, tidal wave, tsunami, flood, damage or destruction by lightning, drought;
    6. explosion, fire, destruction of machines, equipment, factories and of any kind of installation, prolonged break-down of transport, telecommunication or electric current;
    7. general labour disturbance such as but not limited to boycott, strike and lock-out, go-slow, occupation of factories and premises.
      [Page66:]
  4. A party successfully invoking this Clause is, subject to paragraph 6 below, relieved from its duty to perform its obligations under the contract from the time at which the impediment causes the failure to perform if notice thereof is given without delay or, if notice thereof is not given without delay, from the time at which notice thereof reaches the other party.
  5. A party successfully invoking this Clause is, subject to paragraph 6 below, relieved from any liability in damages or any other contractual remedy for breach of contract from the time indicated in paragraph 4.
  6. Where the effect of the impediment or event invoked is temporary, the consequences set out under paragraphs 4 and 5 above shall apply only insofar, to the extent that and as long as the impediment or the listed event invoked impedes performance by the party invoking this Clause of its contractual duties. Where this paragraph applies, the party invoking this Clause is under an obligation to notify the other party as soon as the impediment or listed event ceases to impede performance of its contractual duties.
  7. A party invoking this Clause is under an obligation to take all reasonable means to limit the effect of the impediment or event invoked upon performance of its contractual duties.
  8. Where the duration of the impediment invoked under paragraph 1 of this Clause or of the listed event invoked under paragraph 3 of this Clause has the effect of substantially depriving either or both of the contracting parties of what they were reasonably entitled to expect under the contract, either party has the right to terminate the contract by notification within a reasonable period to the other party.
  9. Where paragraph 8 above applies and where either contracting party has, by reason of anything done by another contracting party in the performance of the contract, derived a benefit before the termination of the contract, the party deriving such a benefit shall be under a duty to pay to the other party a sum of money equivalent to the value of such benefit.


*
ICC Force Majeure Clause and ICC Hardship Clause – ICC Publication No. 650 Copyright © 2003 – International Chamber of Commerce. All rights reserved.