THIS CONTRACT is made on [ ……………………………….., ]

Between:

[……………………………… ] (a […………………………………………….. ]company with registered number [ ]) whose registered office is at [ ……………….] and represented by acting through a duly authorised power of attorney (the Employer, which expression shall include successors and permitted assigns);

and[……………………………………………………. ] (a […………………………………………………. ] company with registered number [……………………………………… ]) whose registered office is at [ ………………………………] and represented by acting through a duly authorised power of attorney (the Contractor, which expression shall include successors and permitted assigns),

each a Party and collectively the Parties.

Whereas

  1. The Employer has decided to appoint the Contractor to design, procure, supply, execute, install, commission, test and hand over, including the remedying of potential defects, on time and within the agreed Contract Price, the Works as defined by the Employer as to scope, purpose, performance and the functions of the Works as set out in the original Employer’s Requirements and the Assumptions and as amended in accordance with the provisions of the Contract;
  2. The Contractor has agreed to such appointment on the terms and subject to the conditions of this Contract as provided herein; and
  3. In this Main Contract Form, all capitalised words and expressions shall have the same meanings as are assigned to them in this Main Contract Form or in the General Conditions.

It is agreed as follows:

  1. The Contractor shall design, procure, supply, execute, install, commission, test and hand over, including the remedying of potential defects, on a Turnkey basis, the Works as described in this Contract, and perform the Works for the compensation provided for herein as more particularly described in the General Conditions of Contract and the Special Conditions attached hereto;
  2. The Employer shall pay the Contractor the price of (the Contract Price) and perform the other actions required of it as more particularly described in the General Conditions of Contract and the Special Conditions attached hereto; and
  3. The following Sections shall be read as one document and form the Contract and, in the event of ambiguity or contradiction between the Sections, the ambiguity or contradiction shall be resolved by giving precedence to the Sections in the order listed as follows:
  • Main Agreement Form
  • Section I—Special Conditions and Appendices thereto
  • Section II—General Conditions of Contract

[Page11:]

Whereas the Parties have executed this Contract by duly authorised representatives on the day and year first above written. 1

EMPLOYER

Name ………………………………….. Witness…………………………..

CONTRACTOR

Name…………………………………….. Witness……………………………….

The remainder of this page has been intentionally left blank.


1
It would generally be good practise to have a witness of the Parties witness all signatures, and examine the ID documents, business cards or powers of attorney of those signing as duly authorized representatives. If appropriate, a chop, stamp or seal for each of the Parties should be attached.