Forgot your password?
Please enter your email & we will send your password to you:
My Account:
Copyright © International Chamber of Commerce (ICC). All rights reserved. ( Source of the document: ICC Digital Library )
Article 45 Completion
45.1 The Contractor shall notify the Employer when it considers that it has achieved Completion of the Works. Where the Works are to be completed by Sections, this Article 45 refers to Completion of each Section as appropriate.
45.2 The Employer shall, as soon as practicable within the period stated in the Special Conditions following receipt of the Notice referred to in Article 45.1, inspect (as and if necessary) all work, and either:
45.3 In the event that the Employer determines that Completion has not been achieved, the Contractor shall promptly take such action or perform such (additional) work as will achieve Completion and shall issue to the Employer another Notice pursuant to Article 45.1. To the extent that the Contractor deems any action or additional work described by the Employer in its Notice under Article 45.2 to be a Variation, the Contractor shall notify the Employer in accordance with the provisions of Article 35. The procedure described in this Article 45.3 shall be repeated as necessary until Completion is achieved.
45.4 Unless otherwise agreed in the Special Conditions, the Employer shall issue the Certificate of Completion or the Notice under Article 45.2(b) no later than five (5) Business Days following receipt of the Notice under Article 45.1. The Employer shall inform the Contractor of the details of the reasons provided in the Notice under Article 45.2(b) within a reasonable time.
45.5 If the Employer fails to issue a Certificate of Completion or a Notice under Article 45.2(b), then the Employer shall be deemed to have, and be treated for all purposes as having, issued a Certificate of Completion, whether it is actually issued or not, no later than the time period set in 45.4, as amended by the Special Conditions as the case may be, after the receipt of the Notice under Article 45.1. The CDB, if the Parties have appointed one, may on application from a Party confirm such Completion, but such confirmation is not a precondition to the effectiveness of any such Completion.
Article 46 Commissioning and Performance Tests and Retest
46.1 Where the Works are to be taken over by Sections, the provisions in this Article shall be read as applying to each Section separately.
46.2 Any commissioning activities shall be set out in the Special Conditions and/or an Appendix thereto as the case may be, or otherwise agreed by the Parties.
46.3 Performance Tests are those tests required to demonstrate the achievement of the Guaranteed Performance as defined in the Special Conditions. Unless otherwise agreed by the Parties, all Performance Tests shall be performed and completed prior to Taking-Over. Unless fully set out in the Contract, the Contractor shall provide the Employer with the Contractor’s methodology for conducting the Performance Test(s) no later than the time set out in the Special Conditions, or if there is no such time set out, the methodology shall be provided at least ninety (90) Days before the tests are to begin. Such methodology shall be in accordance with Good Practice and the relevant requirements of the Contract.
46.4 When the Contractor determines that there are no impediments to conducting the Performance Tests, the Contractor shall give the Employer Notice that it is ready to commence with the Performance Tests.
[Page43:]
46.5 The Contractor shall give the Employer Notice specifying the Date, location and nature of the Performance Test to be conducted:
46.6 Unless otherwise agreed, the Contractor shall afford the Employer all reasonable opportunity to attend all stages of the Performance Test at the Employer’s own expense. Provided that the Contractor has given proper Notice and not prevented the Employer from attending, the Employer’s failure to attend any stage of the Performance Test shall in no way invalidate the results of the Performance Test or permit the Employer to allege that the Taking-Over Conditions have not been fulfilled solely on the basis that a Performance Test the Employer failed to attend was not validly conducted.
46.7 Each Performance Test shall be conducted under the authority and direction of the Contractor. If this Contract specifies that any stage of the Performance Test should be performed by the Employer or a third party appointed by and responsible to the Employer, then the personnel of the Employer or third party shall act under the supervision and instruction of the Contractor.
46.8 If the Employer is under this Contract or otherwise obliged to fulfil any obligation in order to enable the Contractor to perform a Performance Test, and the Contractor has notified to the Employer the timing, nature, quality and extent of the Employer’s obligation in accordance with the Contractor any subsequently agreed or reasonable schedule, then the Employer’s material failure to comply with its obligation shall be treated as a Variation. If the Employer fails on more than one occasion to fulfil any obligation in order to enable the Contractor to perform a Performance Test, without prejudice to any other right it may have, the Contractor may give Notice to the Employer of a final time period of not less than seven (7) Days in which the obligation shall be fulfilled. If the Employer fails to fulfil the said obligation within such time then, unless otherwise agreed, the particular Performance Test shall be deemed, to have been passed and certified, unless otherwise agreed or otherwise required by the laws of the Country,
46.9 The Performance Tests shall demonstrate the performance levels of the Works and whether the Works fulfil the Minimum Performance, if any. In the event that the Works do not achieve the Guaranteed Performance and the Contractor executes remedial Works, the Employer may claim a retest (the “Retest”) to establish that the Works achieve the Guaranteed Performance. Such a Retest shall be subject to the provisions of this Article 46.
Performance-related liquidated damages or bonus for performance
46.10 If the Works fail to achieve the Guaranteed Performance during the Performance Test, and/or the Retest, but do exceed the Minimum Performance, then Performance-related liquidated damages (if any) as set out in the Contract shall be payable.
46.11 The Parties agree and acknowledge that the amounts of liquidated damages (if any) specified in the Contract are agreed upon and fixed by the Parties because of the difficulty of ascertaining on the Contract Date the exact amount of damage to the Employer in such event. The Parties hereby agree that the liquidated damages agreed upon in this Contract shall be applicable regardless of the amount of such damage.
46.12 The payment of any such liquidated damages shall not affect the Employer’s rights to terminate this Contract pursuant to Article 55, should such right exist.
46.13 So long as the performance of the Works is equal to or better than the Minimum Performance, the agreed liquidated damages shall in respect of the relevant performance parameters be the Employer’s sole and exclusive remedy for the Works’ failure to achieve the Guaranteed Performance.
46.14 If so stated in the Special Conditions, the Contractor shall be entitled to a bonus to the extent the performance of the Works is better than the Guaranteed Performance. The performance bonus shall then be calculated in accordance with what is stated in Appendix 46.14 (if any).
Article 47 Taking-Over/Provisional Acceptance
47.1 The Taking-Over/Provisional Acceptance Date shall be:
[Page44:]
47.2 Taking-Over Conditions
Unless the Parties have specified otherwise, the following conditions shall be the Taking-Over Conditions:
47.3 On the Taking-Over Date, the Employer shall take and shall be deemed to have taken possession and control of the entire Works or Section of them and shall thereafter be solely responsible for the operation and maintenance thereof and shall have the complete risk of loss or damage thereto. This shall not relieve the Contractor of its obligations under Chapter 8, or from its obligation to perform such other work as remains to be performed after Taking-Over pursuant to this Contract.
47.4 The Contractor’s access to the Site and the Works after Taking-Over shall be governed by an Appendix (if any) and otherwise shall be permitted as needed to fulfil its remaining obligations (if any).
47.5 If the Works or any Section are to be completed in more than one step or phase, then an Appendix (if any), or such other reasonable stepped or phased schedules as established by agreement, shall apply.
47.6 When the Contractor believes that it has met the Taking-Over Conditions of the Works or any Section in accordance with Articles 47.1 and 47.2, it shall deliver to the Employer a Notice thereof in the form set out in an Appendix (if any), and otherwise any other reasonable form if none is set out.
47.7 The Employer shall, as soon as practicable and in any event within the period agreed in the Special Conditions following receipt of the Notice under Article 47.6, inspect (as and if necessary) all Works and the results of the Performance Tests and, within the time period stipulated in Article 47.9, either:
47.8 In the event that the Employer determines that the Taking-Over Conditions have not been achieved, the Contractor shall promptly take such action or perform such work as will achieve Taking-Over and shall issue to the Employer another Notice pursuant to Article 47.6. To the extent that the action or work requires a Variation, it shall be valued under Article 35. The procedure described in this Article 47 shall be repeated as necessary until Taking-Over is achieved, unless otherwise agreed.
47.9 The Employer shall issue the Taking-Over Certificate or the Notice under Article 47.7 within a reasonable time following receipt of the Notice under Article 47.6. The Taking-Over Certificate shall be retroactive to the Taking-Over Date under Article 47.1. If the Employer fails to issue a Taking- Over Certificate or a Notice under Article 47.7, then the Employer shall be deemed to have, and be treated for all purposes as having, issued a Taking-Over Certificate, whether it is actually issued or not as of the Taking-Over Date. The Employer shall not be entitled to withhold payments claimed by the Contractor on the basis that the Taking-Over Certificate was not issued or properly issued due to a failure by the Employer.
47.10 The Taking-Over Certificate, whether deemed to be issued or actually issued, shall operate as an acknowledgement by the Employer that the Contractor has fulfilled its obligations under this Contract to the extent that this Contract called for such obligations to be performed prior to Taking-Over, except for such work (whether minor or not) as is mutually acknowledged to remain outstanding, whether under a punch list, snag list or other check list of outstanding work to correct Defects (the “Punch List”).
[Page45:]
47.11 If the Taking-Over Certificate was deemed to have been issued by the Employer, then the Employer shall be entitled to require the Contractor to fulfil any Contractor obligations left unfulfilled at Taking-Over. Such work and the work required under Article 47.10 shall be performed at the Contractor’s expense.
Article 48 Assessment procedures after Taking-Over
48.1 To the extent the Parties have agreed in the Special Conditions that certain assessment procedures are to be or permitted to be conducted after Taking-Over, the provisions agreed between the Parties with respect to such procedures shall apply. Where no agreement has been made on how the assessment procedures after Taking Over shall be conducted, they shall be conducted according to Good Practice.
48.2 If there are no such procedures set out the Special Conditions, then Article 47.4 shall apply.
48.3 If for reasons not attributable to the Contractor, any tests after Taking-Over cannot be completed during the Defect Correction Period (or any other period agreed upon by both Parties) then the Works shall be deemed to have passed the tests after Taking-Over.