Article

Factual Summary:

To assure construction of improvements required by a residential development zoning plan, the applicant obtained issuance of a standby LC. The standby required presentation of a statement to the effect that improvements were not satisfactorily performed and that the sum demanded was owed to the Township as a result.

According to the Complaint, the completion of the improvements required access to adjoining property that the beneficiary had agreed to obtain, that the applicant had paid the beneficiary to obtain such access, that it had failed to act, that it had amended the zoning plan to prohibit development of adjoining lots, and that it had wrongfully drawn down $55,495 on the standby. The applicant contended that these actions amounted to an unconstitutional deprivation of property in violation of his right to due process. The applicant argued that he had a right to prompt release from liability after completing improvements and a specific statutory entitlement to have his funds used only for the purposes agreed.


Legal Analysis:

The court rejected these arguments, ruling that the requisite protected interest in property was absent. The court noted that general contract rights are not property protected by the Due Process Clause of the Constitution unless they are a contract to protect a conferred status or can be terminated only for cause, neither of which was applicable. Moreover, the court concluded that even if there were a due process right, it was waived by virtue of the terms of the letter of credit which permitted drawing by demand and without notice. "The plaintiff is a real estate developer. He cannot now be heard to complain that the funds were taken without notice when the [beneficiary] did what he explicitly agreed that it could do." The contract claims were dismissed with the notation that they could be raised in an action in the state courts.

©2000 INSTITUTE OF INTERNATIONAL BANKING LAW & PRACTICE

COPYRIGHT OF THE INSTITUTE OF INTERNATIONAL BANKING LAW & PRACTICE

The views expressed in this Case Summary are those of the Institute of International Banking Law and Practice and not necessarily those of ICC or the other partners in DC-PRO.