Forgot your password?
Please enter your email & we will send your password to you:
My Account:
Copyright © International Chamber of Commerce (ICC). All rights reserved. ( Source of the document: ICC Digital Library )
2015 LC CASE SUMMARIES 2015 SGHC 57 (March 4, 2015) [Singapore]
Topics: Unconscionability; Injunction; Classification
Type of Lawsuit: Application by Developer/Beneficiary to set aside an ex parte injunction obtained by Contractor/Applicant against drawing on a performance bond.
Parties: Plaintiff/Contractor/Applicant: JK Integrated
Developer/Beneficiary: 50 Robinson
Issuer: QBE Insurance (International)
Underlying Transaction: SGD 47,000,000 construction contract for residential/commercial building.
LC: Performance bond for SGD 4,700,000.
Decision: The High Court of Singapore, Hoo Sheau Peng, JC., set aside the ex parte injunction against Developer/Beneficiary and ordered Contractor/Applicant to pay costs to Developer/Beneficiary.
Rationale: Where no prima facie case of unconscionable conduct on the part of the Beneficiary is proven, an injunction will not issue. A mistaken call on a performance bond can only be enjoined if it was made in bad faith. Areas of genuine dispute between the parties do not satisfy the test of unconscionability, but is abusive conduct.
Article
Factual Summary: As the main contractor on a building project worth SGD 47,000,000, Contractor/Applicant provided Developer/Beneficiary with a performance bond for SGD 4,700,000, issued by Issuer. The opinion did not indicate that it was subject to any practice rules.
Construction began in September 2011 and was scheduled to be completed in February 2014. After several months of smooth and prompt work, delays began in March 2012. Though Contractor/Applicant requested extensions, Developer/Beneficiary only granted a 9-day extension, moving the completion date to 9 March 2014, because it claimed that the delays were caused by Contractor/Applicant.
Contractor/Applicant encountered repeated financial difficulties because its 35 claims for payment between September 2011 and June 2014 were not paid in full. Developer/Beneficiary countered, however, that payments were made according to joint assessments of completed work established in the contract and referenced meeting notes and correspondence as evidence of Contractor/Applicant’s concession to this fact. Nonetheless, Developer/Beneficiary did give Contractor/Applicant two advance payments of SGD 500,000 and SGD 1,300,000, per Contractor/Applicant’s request.
After continued delays and an extension request from Contractor/Applicant, Contractor/Applicant and Developer/Beneficiary entered into a Supplemental Agreement that provided Contractor/Applicant with the funds to complete the project, subject to monitoring of where the payments were applied and an updated completion schedule. Under the Supplemental Agreement, Contractor/Applicant was required to raise SGD 1,000,000 from its shareholders within 5 days of the Supplemental Agreement being signed. However Contractor/Applicant did not raise the money until 12 days after the Supplemental Agreement, but did raise SGD 1,400,000. Furthermore, Contractor/Applicant was required to use the SGU 680,000 provided by Developer/Beneficiary only to pay outstanding debts related to the project. Instead it used some of the money to pay for materials related to the project.
In September 2014, when the architect involved in the contract terminated its relationship with Contractor/Applicant, Developer/Beneficiary subsequently did the same, and demanded payment of SGD 4,700,000 on the performance bond. Contractor/Applicant applied for and obtained an ex parte injunction against Developer/Beneficiary for the drawing on the performance bond on the ground that Developer/Beneficiary’s conduct was unconscionable. When Developer/Beneficiary applied to have the injunction set aside, the Judge granted the application, setting aside the injunction.
Legal Analysis:
The Judge further ruled that Contractor/Applicant failed to demonstrate the delay in work was a result of Developer/Beneficiary’s conduct. Rather, the Judge agreed with Developer/Beneficiary’s argument that Contractor/Applicant was responsible for the delays. Furthermore, the Judge ruled that Developer/Beneficiary’s agreement to advance payments to Contractor/Applicant notwithstanding the delays evidenced a clear lack of the alleged bad faith on the part of Developer/Beneficiary.
The Judge noted that unconscionability is a basis for interrupting payment on a demand guarantee. The Judge stated that “[u]nconscionability is an amorphous concept that is easily identifiable, but difficult to define” and that what constitutes unconscionability “depends on the facts of each case.” Genuine mistakes by the beneficiary, “mere breaches of contract by the beneficiary, or genuine disputes between the parties, are insufficient to constitute unconscionability.”
Noting that payment was predicated on the issuance of architects certificates and that there was no allegation of fraud or improper pressure on the architect the Judge ruled that there was convincing proof that Developer/Beneficiary had acted improperly or in bad faith.
Contractor/Applicant argued that discrepancies and lack of detail in the construction plans caused loss and delay which impeded performance and caused minor breaches. Considering the claims, the Judge concluded “mere breaches of contract by the beneficiary, or genuine disputes between the parties are insufficient to constitute unconscionability.”
Contractor/Applicant also contended that Developer/Beneficiary’s failure to make payments caused delays on payments to subcontractor, workers, and suppliers. Noting that advance payments had been made, the Judge indicated the opinion that the delays were attributable to the conduct of Developer/Beneficiary.
Contractor/Applicant alleged that claims regarding application of funds, adherence to a time table, and replacement of personnel were unconscionable. The Judge noted that there were genuine disputes, none of which suggested unconscionable conduct. Nor did the Judge agree that the demands for proof of use of funds and threats of nonpayment were unconscionable in light of the relationship and agreement.
Contractor/Applicant also asserted that the termination of the contract was unconscionable. The Judge noted that Developer/Beneficiary terminated the agreement on receipt of a certificate from the architect and, so, was “entirely honest, reasonable, and genuine”.
Comments:
Relevant terms from the performance bond, excerpted from the opinion:
“1 In consideration of the Employer not insisting on the Contractor paying ten percent (10%) of the Contract Sum as a security deposit for the Contract, we hereby irrevocably and unconditionally warrant and guarantee the due and faithful performance of the Contract by the Contractor.
2 We unconditionally and irrevocably undertake and covenant to pay in full forthwith upon demand in writing any sum or sums that may from time to time be demanded by the Employer up to a maximum aggregate sum of Singapore Dollars Four Million and Seven Hundred Thousand Only (S$4,700,000.00) (hereinafter referred to as “the Maximum Aggregate Sum”) without further reference to the Contractor and without requiring any proof that the Employer is entitled to such sum or sums under the Contract or that the Contractor has failed to execute the Contract or is otherwise in breach of the Contract. Any sum or sums so demanded shall be paid forthwith by us, unconditionally without any set- off deductions or counter-claims whatsoever and notwithstanding the existence of any differences or disputes between the Employer and the Contractor arising under or out of or in connection with the Contract or the carrying out of works thereunder or as to any amount or amounts payable thereunder and notwithstanding that such differences or disputes have been referred to arbitrator or are the subject of proceedings in Court and notwithstanding any instruction which may be given to us by the Contractor not to pay the same or any part thereof.
3 We hereby confirm and agreed [sic] that we shall be under no duty or responsibility to inquire into:-
(a) the reason or circumstance of any demand hereunder; or
(b) the respective rights, obligations and/or liabilities of the Contractor and the Employer under the Contract ...
...
5 Our liability hereunder shall not be discharged, affected or impaired or otherwise released in any way by reason of any modification, amendment or variation in or to any of the conditions or provisions of the Contract or by reason of any breach or breaches of the Contract by the Contractor, whether the same are made with or without our knowledge or consent.”
[ALC]
COPYRIGHT OF THE INSTITUTE OF INTERNATIONAL BANKING LAW & PRACTICE
The views expressed in this Case Summary are those of the Institute of International Banking Law and Practice and not necessarily those of the ICC or Coastline Solutions.