Forgot your password?
Please enter your email & we will send your password to you:
My Account:
Copyright © International Chamber of Commerce (ICC). All rights reserved. ( Source of the document: ICC Digital Library )
2015 LC CASE SUMMARIES Arbitration Petition (L) No. 647 of 2015 (Bombay H.C. 2015) [India]
Topics: Injunction; Characterization; Arbitration petition; Fraud; Injustice; Independence
Type of Lawsuit: Applicant/Contractor sued Beneficiary/Purchaser seeking an interim injunction that would prevent Beneficiary/Purchaser from drawing on two bank guarantees and prevent Guarantor from honoring drawings pending resolution of an arbitration proceeding on the underlying agreement.
Parties: Petitioner/Applicant/Contractor: M/s. S. Satyanarayana and Co. (Counsel: V. Dhond)
Respondent 1/Beneficiary/Purchaser: M/s. West Quay Multiport Pvt. Ltd. (Counsel: S.U. Kadmar, Dharam Jumani, and Ganesh & Co.)
Respondent 2/Guarantor: Anr. (Counsel: S.U. Kadmar, Dharam Jumani, and Ganesh & Co.)
Underlying Transactions: Two 12-month contracts for supply of materials and labor for the construction of a compound wall at stack yard of a vessel berth at the port of Visakhapatnam, India.
Guarantees: Two bank guarantees for ten percent of the contract value, valid for twelve months, guaranteeing the contract’s due performance subject to governing rules.
Decision: The High Court of Judicature at Bombay, Gupte, J., dismissed the petition for an interim injunction.
Rationale: To warrant injunctive relief, there must be either fraud or irretrievable injustice. It is not sufficient to allege that a drawing was “evidently wrongful” or made in bad faith or for an extraneous purpose.
Article
Factual Summary: Purchaser contracted with Contractor to construct a berth for a vessel. To protect Purchaser from loss or damage resulting from breach by Contractor, the Construction Agreements required two bank guarantees in favor of Purchaser.
As issued, the guarantees could be drawn upon Applicant/Contractor’s default of the contract or upon other occurrences such as failure to remedy construction irregularities in the eighteen months following completion. The opinion stated that “[t]he guarantees were to be enforceable without any requirement to place any demand on the [Applicant/Contractor] for any amount and notwithstanding any dispute between the parties in respect of the alleged default”. Both guarantees “unconditionally and irrevocably” undertook to pay to Beneficiary/Purchaser the available amounts, "against any loss or damage caused to or suffered or would be caused to or suffered by [Beneficiary/Purchaser] by reason of any breach by the contractor of any of the terms and conditions contained in the [contract]. The bank undertook to pay the amounts without demur merely on a demand from the [Beneficiary/Purchaser] stating that the amount claimed is due by way of loss or damage by such reason” (internal quotation marks and citations omitted).
Beneficiary/Purchaser issued an “experience certificate” confirming Applicant/Contractor’s completion of the work and did not inform Applicant/Contractor of any grievances regarding the timeliness or quality of the work.
Nine months later, Beneficiary/Purchaser sent two letters to Applicant/Contractor alleging breach of contract. On the same day, Applicant/Contractor received notice from Guarantor that Beneficiary/Purchaser had drawn on both bank guarantees. Claiming that the drawing was fraudulent and would cause Applicant/Contractor irretrievable injustice, Applicant/Contractor sued Beneficiary/Purchaser and Guarantor seeking an interim injunction. The petition was denied.
Legal Analysis:
Although Applicant/Contractor cited several foreign cases in support of expanding the definition of fraud, the Judge either differentiated those cases from the facts or ruled that due to the lack of ambiguity in Indian law on matters concerning fraud and injunctive relief, Indians courts need not rely on foreign case law. The Judge stated that Applicant/Contractor had no basis for questioning Beneficiary/Purchaser’s motive in drawing on the guarantees.
Applicant/Contractor also argued that because Beneficiary/Purchaser certified the completion of the contract, Beneficiary/Purchaser had to consult with Applicant/Contractor first before drawing on the guarantees. Beneficiary/Purchaser disagreed, however, stating that the experience certificate was not for the completion of the contract but functioned only as a certificate required by another contract. The Judge, in agreeing with Beneficiary/Purchaser, ruled the certificate did not affect the guarantee because the guarantee was a separate and independent contract. The Judge opined that Applicant/Contractor may seek a refund of the amount paid under the guarantee afterward, which rendered Applicant/Contractor’s harm not irretrievable.
The Applicant/Contractor asserted that Beneficiary/Purchaser should be enjoined from drawing on the guarantees to order to repair the damaged work. The damages were the result of an earthquake and could be remedy under the contract. The Judge disagreed stating “[t]hese are all matters pertaining to the underlying contract, with which the guaranteeing bank is not in any way concerned.
2. Independence. The Judge stated that “[t]he law concerning invocation of, and payment under, a bank guarantee is now well settled and hardly admits of any ambiguity or doubt”. Noting that a bank guarantee is “an independent contract between the bank and the beneficiary thereof” that must be honored provided that the drawing complies “[i]rrespective of any dispute between the beneficiary and the party at whose instance the bank guarantee is furnished…”. In discussing the independence principle, the Judge noted that “[t]he only two exceptions are fraud and special equities which imply an irretrievable injury or injustice. The fraud itself must be of an egregious nature so as to vitiate the entire underlying transaction. Even irretrievable injury or injustice would imply some executional circumstance which would make it impossible for the guarantor to reimburse himself if he were to ultimately succeed, there being good prima facie case of such success.” [emphasis supplied]
EXCERPTS FROM TEXT OF GUARANTEES:
“against any loss or damage caused to or suffered or would be caused to or suffered by the client by reason of any breach by the contractor of any of the terms and conditions contained in the ‘[contract]’.”
“merely on a demand from the client stating that the amount claimed is due by way of loss or damage.”
Comment: “Unconditional”. The opinion stated that “Irrespective of any dispute between the beneficiary and the party at whose instance the bank guarantee is furnished, the bank is obliged to honour the guarantee, if such guarantee is unconditional and irrevocable.”
Independent undertakings are by their nature conditional on the timely presentation of complying documents.
[SRJ/MJK]
COPYRIGHT OF THE INSTITUTE OF INTERNATIONAL BANKING LAW & PRACTICE
The views expressed in this Case Summary are those of the Institute of International Banking Law and Practice and not necessarily those of the ICC or Coastline Solutions.